Despite a rash of rainy weather, work continues both inside and outside the new building. The fuel island canopy is currently being installed, the roof panel installations are complete, and the siding panels are currently going up. The building is now encapsulated. Temporary heat has been installed and activated, and the bus warmer electrical panel and outlets are fully installed and operational. The decorative stone facade work also continues to make progress.

Both the mechanical and main mezzanines have been installed; the concrete for the main mezzanine has been installed which has opened up work for all trades. Fire caulking, insulation, metal stud and drywall is being installed on both the first and second floor levels. The mechanical, electrical and plumbing contractors are also continuing their work on the first and second floor levels.