The Transportation Center has been completed and is fully operational, however September brings more updates to the facility.

These items include:

  • The fencing, automated gates, radiant heat sidewalks, staff and bus parking lot areas have been installed and are in use by the district.
  • The fuel island is fully operational.
  • Minor parking lot punch out work is ongoing and will be completed by the end of September.
  • The General Trades contractor has completed the installation of all exterior components.  Minor punch out work is ongoing and will be completed by the end of September.
  • Landscaping is being finalized.