Outdoors, the curbing and sidewalks are currently being installed around the new building, along with the under-slab radiant heating. Installation of the oil separator and retention pond have also been completed. Nearly all exterior components have been fully installed on the new building at this point, with only soffits and fascia on the building’s west side remaining. These will be applied after removal of the existing building, when there will be adequate space for the contractors to perform the west façade work. Inside the new building, interior finish work has been completed on both the first and second levels. Mechanical, electrical, and plumbing work continues to progress on schedule. The boilers and air handling unit are up and running, and the elevator installation is nearly complete — the elevator itself has been installed, and programming is currently underway. Both the bus wash equipment and fire alarm system are also complete and on track for testing later this month. As the new building nears substantial completion, “punch list” items are being identified and addressed to allow for building access in late May. The demolition plan for the old facility, along with the remaining exterior and site work that will follow, are currently being finalized to allow for final project completion in August.