The fuel island and canopy work is now complete, with testing planned for spring. In addition to the roofing panels, the exterior siding panels, stone facade and interior liner panels are now complete. The overhead doors and windows are currently being installed, and the gutters have been installed and tied into the new storm water system.

Work inside continues to develop as interior finish work continues. All of the interior radiant heat loops, trench drains and concrete slabs are in place, and stair tower installation has also begun. The metal stud work and drywall finish is now 95% complete, and most of the area is primed and ready for painting. Tile work has commenced in the upper restrooms.

The mechanical, electrical and plumbing contractors are continually installing roughing-in work on the first and second floor levels. The boilers and air handling units have been installed, and duct work installation is ongoing throughout the facility. In addition, the fire suppression system is currently 85% complete and mechanical finishes are currently being installed.